Supplier scorecard template that fills itself from your POs

A supplier scorecard shows which suppliers deliver what they promise, so you know whose dates you can plan on and whose parts need more buffer or a second source. Build it from the dates on your POs and the scores hold up when you put them in front of the supplier.

Prefer a spreadsheet? Download the free supplier scorecard template for Excel, which also opens in Google Sheets. No sign-up.

What is a supplier scorecard?

A supplier scorecard turns your PO history into one score per supplier. It counts how often each supplier delivered by the date it confirmed, by the date you asked for, and in full. It measures how far the supplier’s lead time strayed from its quote and how fast it answered your PO. Weights set how much each measure counts, and bands turn the score into a decision: buy more, agree one improvement, or qualify a second source.

Build it from dates rather than ratings. A buyer who rates suppliers from memory remembers the last bad week, while the dates on your POs hold every delivery, and a supplier can check them line by line.

Download the template for Excel or Google Sheets

The supplier scorecard template is an Excel workbook with live formulas and the same rules as the online version below. It holds four sheets:

  • PO lines: one row per PO line, columns A to L, with the illustrative example filled in. Paste your own export over it.
  • Settings: weights that must total 100, the grace days, in-full tolerance, lead-time window, acknowledgement target and score bands.
  • Scorecard: one row per supplier with every rate, the days versus confirmed, the lead-time spread, the score and its band.
  • Read me: the rule behind each measure.

To use it in Google Sheets, open a new sheet and choose File, then Import, and upload the file. If you only need the column headers for an ERP export, take the blank CSV template.

Decide which date each measure uses

Most arguments about a scorecard turn on which date counts. Settle it before you score anyone. These are the rules the template applies:

Fig. 1: The date and quantity behind each measure
MeasureDates and quantities usedRule
On time to confirmationReceived date against the supplier’s confirmed dateLines received on or before the confirmed date plus grace, divided by lines with a confirmed date
On time to requestReceived date against your requested date, as it stands nowLines received on or before the requested date plus grace, divided by lines with a requested date
In fullTotal received quantity against ordered quantityLines with received quantity at or above ordered quantity × (1 − tolerance), divided by lines with both quantities
OTIFOn time to the date you choose (confirmed by default) and in fullLines that are both, divided by lines with data for both
Lead-time adherenceReceived date minus confirmed date, which equals actual lead time minus quoted lead timeShare of lines within ± the window; mean and standard deviation of the difference in days
Acknowledgement timeFrom the time you sent the PO to the time the supplier acknowledged it, once per POMedian hours; share of POs acknowledged within the target. A PO never acknowledged counts as missed
Open linesNo receipt, judged on the as-of datePast the confirmed (or requested) date: late and short. Not yet due: left out

Early deliveries count as on time. If early stock costs you space or cash, watch lead-time adherence: a line three days early falls outside a window of plus or minus two days.

Score your suppliers from your PO lines

The template opens on four illustrative suppliers, so you see a complete scorecard before you change anything. Paste your own PO lines into the first step or upload a CSV, then open the other steps to set weights, rules and bands. Your settings travel in the page link, and your PO lines stay in your browser.

Supplier scorecard template

Paste an export from your ERP or a spreadsheet, upload a CSV, or edit the example. Nothing leaves your browser.

Excel template Blank CSV
Columns the scorecard reads
supplierSupplier name or number
poPO number
linePO line number
partPart number (optional)
qty_orderedQuantity ordered on the line
qty_receivedQuantity received so far
po_sentDate and time you sent the PO (optional)
acknowledgedDate and time the supplier acknowledged it (optional)
requested_dateDate you need it, as it stands now
original_requested_dateRequested date on the first PO, if your team moved it (optional)
confirmed_dateDate the supplier confirmed
received_dateDate of the last receipt; blank if nothing arrived

The scorecard matches header names loosely, so "Vendor", "Promise date" or "Receipt date" also work. Dates can be 2026-05-21, 5/21/2026 or 21.05.2026; add a time (2026-05-21 14:30) to the PO sent and acknowledged columns to get acknowledgement time in hours. If a line arrived in several receipts, give each receipt its own row: the scorecard adds the quantities and takes the last receipt date.

Weight each measure by what a failure costs you.

Total 100 of 100.

Below 70 a supplier lands in Review. Set your own cut-offs.

Illustrative example: 38 PO lines from four invented suppliers of castings, fasteners, packaging and resin. Replace them above with your own.

Suppliers scored

4

PO lines scored

38

Best score

84.2

Suppliers in Review

2
Harbor Castings keeps its own dates and promises late. It delivered 75.0% of its lines by the date it confirmed and 0% by the date you asked for. Ask for a shorter quoted lead time, or order earlier.

Data quality: 38 of 38 lines scored. 1 open past due, counted late and short. 1 with no confirmed date, left out of on time to confirmation and lead-time adherence. 3 where your team moved the requested date; on time to request uses the latest date. 1 supplier under 10 lines: treat that score as a hint.

Scores by supplier

SupplierScoreOn time to confirmationOn time to requestIn fullOTIFLead-time adherenceDays vs confirmedmean, σAcknowledgementmedianLinesscored of total
84.2Approved83.3%10 of 1275.0%9 of 1291.7%11 of 1275.0%9 of 1266.7%8 of 12+0.1 dσ 2.4 d3.0 h6 POs12of 12
Small sample77.9Conditional66.7%2 of 375.0%3 of 4100%4 of 466.7%2 of 366.7%2 of 3+2.0 dσ 4.4 dn/a4of 4
60.0Review75.0%9 of 120%0 of 12100%12 of 1275.0%9 of 1283.3%10 of 12-0.1 dσ 1.4 d47 h6 POs12of 12
57.0Review60.0%6 of 1040.0%4 of 1060.0%6 of 1040.0%4 of 1080.0%8 of 10+1.6 dσ 4.9 d25 h5 POs10of 10

Working

  1. On time to confirmation

    10 of 12 lines received on or before the supplier's confirmed date = 83.3%.

  2. On time to request

    9 of 12 lines received on or before your requested date = 75.0%.

  3. In full

    11 of 12 lines received at least the full ordered quantity = 91.7%.

  4. OTIF

    9 of 12 lines both on time to the confirmed date and in full = 75.0%.

  5. Lead-time adherence

    8 of 12 lines arrived within ±2 days of the confirmed date = 66.7%. Received minus confirmed averages +0.1 days with a standard deviation of 2.4 days.

  6. Acknowledged in time

    6 of 6 POs acknowledged within 24 hours of sending = 100%. Median 3.0 hours.

Weighted score

On time to confirm30 × 83.3%25.00
On time to request15 × 75.0%11.25
In full25 × 91.7%22.92
Lead-time adherence15 × 66.7%10.00
Acknowledged in time15 × 100%15.00
ScoreSum of points84.2

Band: Approved (90 and up Preferred, 80 Approved, 70 Conditional, below that Review).

Lead time

Quoted lead time (confirmed date minus PO sent) averages 21.2 days. Actual lead time (received minus PO sent) averages 21.3 days, standard deviation 2.4 days, over 12 lines. Use that spread as σLT in the safety stock calculator: a steady supplier earns a smaller buffer at the same service target.

σL ÷ L = 2.4 ÷ 21.3 = 0.11. Under 0.25: this supply counts as reliable.

Data quality

  • 12 of 12 lines scored.

Read the scorecard before you share it

Start with the two on-time columns side by side. A supplier with high on time to confirmation and low on time to request keeps its promises and promises late. Treat that as a lead-time or capacity problem, and fix it with a new quote or by ordering earlier. If both rates are low, the supplier misses dates it set itself, and you have a stronger case for escalation.

Then read in full beside OTIF. A packaging supplier that rounds each order down to a full pallet scores high on time and low in full. Decide whether you’re looking at a short ship or a pack size you should order to.

The days versus confirmed column shows the average and the spread. A supplier with a mean near zero and a standard deviation of five days hurts your plan more than one that runs two days late each time, because you can plan around a steady two days.

Read the data-quality line before you share anything. If a score rests on four lines or on a column of missing confirmed dates, collect better data before you judge the supplier.

Four measures come from PO dates

A PO export tells you whether the part arrived on time, whether it arrived in full, how far the supplier’s actual lead time strayed from its quote, and how fast the supplier answered your PO. Those four make up the delivery half of a scorecard.

Quality, price and compliance need other sources

Take defect and return rates from receiving inspection and your nonconformance log, price variance from invoices against PO price, and certificates or audit results from your supplier files. Add each as a column in the downloaded scorecard with its own weight, and note its source beside it.

How each measure is calculated

On-time delivery: requested, confirmed and grace

Your requested date is when you need the part. The confirmed date is what the supplier committed to. Score against both. If your team moved the requested date after the PO went out, put the first date in original_requested_date. The template counts the moves and measures against the latest date, so it won’t mark a supplier late for a date you abandoned. A grace window of one or two days suits parts with buffer stock. For parts that feed a line, keep grace at zero.

In full: tolerance, split shipments and short ships

A line counts as in full when the total received reaches the ordered quantity, less any tolerance you set. The template adds up several receipts against one line and takes the last receipt date as the delivery date. A line with nothing received past its due date counts as late and short on the as-of date, so a supplier can’t lift its score by not shipping.

Lead-time adherence: average and spread

Quoted lead time is the confirmed date minus the date you sent the PO. Actual lead time is the received date minus the same send date. Their difference equals received minus confirmed, in days. The template reports the mean, the standard deviation and the share of lines inside your window.

That spread sets the buffer. A supplier whose lead time varies little gets a smaller safety stock at the same service target, and you change no setting to get it. Divide the standard deviation of actual lead time by its mean: above about 0.25, treat the supply as unreliable. The safety stock calculator takes that standard deviation as σLT in SS = Z × √(LT × σd² + d² × σLT²), so one PO export feeds both. The lesson on supplier lead time explains why the spread matters more than the average.

When timing is the risk

When late receipts are the risk and demand holds steady, a safety lead time can beat safety stock: plan the receipt a few days before you need it and hold fewer units. Short shipments are a separate risk. σLT measures timing, so a supplier that ships 95% of each order needs a yield allowance on the order quantity. The in-full column shows how often that happens.

Acknowledgement time: what starts and stops the clock

The clock starts when you send the PO and stops when the supplier acknowledges it. The template measures it once per PO and reports the median, so one PO lost over a holiday can’t skew it. Give both columns a time of day, or the hours round to whole days. A PO with a send time and no acknowledgement counts as missed, since that silence is the failure you’re measuring.

Turn the measures into one score

Weight each measure by what a failure costs you

For a casting that stops final assembly, put most of the weight on on time to request and in full. For MRO supplies, acknowledgement time and price matter more than a two-day slip. The defaults fit direct materials with some buffer stock:

Fig. 2: Default weights, and when to move them
MeasureDefault weightRaise it when
On time to confirmation30You plan production on the supplier’s confirmed dates
On time to request15The part feeds a line with little buffer
In full25A short ship stops a build, or the supplier rounds to pack sizes
OTIF0You want one delivery measure in place of the three above
Lead-time adherence15Lead-time swings set your safety stock
Acknowledged in time15Unconfirmed POs keep your planners guessing

OTIF starts at zero because it repeats on time and in full; give it weight if you drop those two.

Worked example: a fastener supplier

Take Keel Fasteners from the illustrative example: 12 PO lines, all received.

Fig. 3: Keel Fasteners scores 84.17, in the Approved band
MeasureRateWeightPoints
On time to confirmation10 of 12 = 83.33%3025.00
On time to request9 of 12 = 75.00%1511.25
In full11 of 12 = 91.67%2522.92
Lead-time adherence (±2 days)8 of 12 = 66.67%1510.00
Acknowledged within 24 hours6 of 6 POs = 100%1515.00
Score10084.17

Received minus confirmed averages +0.08 days with a standard deviation of 2.35 days, and the median acknowledgement takes 3 hours. Select the supplier in the template to see each number worked out.

Status bands and what to do at each

The default bands are 90, 80 and 70. Treat them as a starting point and set your own. For parts that stop a line, the stricter option under the bands sets them at 98, 95 and 90.

  • Preferred: offer more volume or longer agreements, and review quarterly.
  • Approved: share the scorecard and the lowest measure, and agree one improvement.
  • Conditional: review monthly, ask for a recovery plan, and check your own safety stock on their parts.
  • Review: qualify a second source for the parts that can stop a line.

When the scorecard lies

A score is only as fair as the lines behind it. Check these before you act on one.

Small samples

With 4 lines, one late delivery moves a rate by 25 points. The template flags suppliers under your minimum and shows a 95% range in the working: 3 of 4 could mean anything from 30% to 95%.

Dates your team moved

If a buyer pushed a requested date out, the supplier shouldn’t count as late against the old one. Add an original requested date column so the template can tell the two apart.

Padded confirmations

A supplier that confirms each PO three weeks out will hit 100% on time to confirmation. On time to request and quoted lead time show the padding. Harbor Castings in the example follows this pattern.

Overwritten confirmed dates

Your ERP may keep only the latest confirmed date. If the supplier re-confirmed a day before delivery, on time to confirmation scores the last promise. Keep the first confirmed date if your system allows it.

One big PO and many small ones

The template counts lines, so 50 lines of washers outweigh one line of castings worth ten times as much. If that distorts the picture, score critical parts on their own.

Early deliveries

They count as on time and still tie up cash and space. Watch the lead-time adherence column, where early lines fall outside the window.

Missing dates

Lines with no confirmed date drop out of two measures and don’t count as failures. If one supplier accounts for most of the gaps, raise the missing dates with that supplier.

Review the score with your supplier

Score suppliers that can stop a line monthly and the rest quarterly, over a rolling window that holds at least 10 to 20 lines each. A rolling 12 months suits most suppliers. Send your supplier the downloaded CSV with the rules in Fig. 1, so the meeting covers late parts and skips the arithmetic.

To score by part, put the part number in the supplier column. To compare plants, add the plant to the supplier name, such as “Keel Fasteners / Plant 2”. A part you buy from two suppliers then shows up as two rows side by side. The lessons on purchase order tracking and promise date versus need date cover how to collect the dates.

Your scorecard is only as current as the confirmed and received dates in your export. Cartograph follows up on open POs: Scout Agent emails and calls suppliers to confirm dates and expedite late lines, and Cartograph records the promised and actual dates on each PO line. Get Cartograph free to see it on your own POs.

Supplier scorecard questions

Is there a free supplier scorecard template in Excel?

Yes. Download the supplier scorecard template from this page: an Excel workbook with live formulas that also opens in Google Sheets. Paste your PO lines into one sheet and the scorecard sheet rates each supplier on time to confirmation, on time to request, in full, OTIF, lead-time adherence and acknowledgement time, with weights and bands you set. No sign-up.

What should a supplier scorecard include for a manufacturer?

Start with the delivery measures you can take from PO dates: on time to the supplier's confirmed date, on time to your requested date, in full, lead-time adherence and how fast the supplier acknowledges a PO. Then add quality (defects and returns from receiving inspection), price variance from invoices, and compliance from your supplier files, each with its own weight.

How many metrics should a supplier scorecard have?

Five to eight. Fewer than five hides where a supplier fails; more than eight spreads the weight so thin that no single failure moves the score. The template uses six delivery measures, one of which starts at zero weight.

How do you calculate a supplier scorecard score?

Turn each measure into a rate out of 100, multiply it by its weight, and add the results. With weights that total 100, the sum is the score out of 100. If a supplier has no data for a measure, drop that measure, divide the points by the weights that remain, and multiply by 100.

Should I measure on-time delivery against the requested or the confirmed date?

Measure both and keep them apart. On time to confirmation tells you whether the supplier keeps its word. On time to request tells you whether the part arrived when you needed it. A supplier that confirms three weeks late and then hits its own date scores high on the first and low on the second. Raise that gap with the supplier.

How do you score partial shipments?

Judge the line on its total. Add up the receipts against the PO line, compare the total with the ordered quantity for in full, and use the date of the last receipt for on time. For a finer measure, credit each receipt's quantity on its own date.

What is lead-time adherence?

Lead-time adherence compares the lead time a supplier quoted with the lead time it delivered. Quoted lead time is the confirmed date minus the date you sent the PO; actual lead time is the received date minus the same send date. The difference equals received minus confirmed, in days. Report its mean, its standard deviation and the share of lines inside a window such as plus or minus two days. A supplier whose lead-time standard deviation is more than about a quarter of its mean lead time is unreliable supply and needs a larger buffer.

How often should I review a supplier scorecard?

Review suppliers that can stop a line monthly and the rest quarterly. Use a rolling window that holds at least 10 to 20 PO lines per supplier; with fewer, one delivery swings the rates. A rolling 12 months suits most suppliers.

What is a good on-time delivery rate for suppliers?

We know of no sourced industry benchmark for small and mid-size manufacturers. Set your target from what a late part costs you. For parts that stop a line, hold suppliers to 98% and treat anything under 90% as a reason to qualify a second source.

Can I build the scorecard from my ERP or a PO export?

Yes. Export PO lines with the supplier, PO and line number, ordered and received quantity, the requested, confirmed and received dates, and, if your system has them, the PO send and acknowledgement times. Paste the export into the template above or upload it as a CSV.

What is the difference between a supplier scorecard and a supplier evaluation?

A supplier evaluation decides whether to work with a supplier, usually before the first order, from audits, quotes and references. A supplier scorecard rates a supplier you already buy from, on what it delivered, and you repeat it each month or quarter.

What should happen after a low score?

Share the scorecard and the rules behind it with the supplier, name the one measure that pulled the score down, and agree a fix and a date. Review monthly until the score recovers. For parts that can stop a line, qualify a second source while you wait.

Why do supplier scorecards fail?

Three reasons come up most. Ratings typed from memory lose the supplier's trust, missing confirmed dates leave the delivery measures empty, and a score no one acts on turns into a report. Build the score from PO dates, collect the confirmed date on every PO, and attach one action to each band.

How do I score a supplier with few POs?

Show the score and flag it. With 4 lines, one late delivery moves the on-time rate by 25 points. For small samples the template shows a 95 percent range, so you can see how little the number proves yet.